Chip Seal Program
The 2025 County/ City Chip & Seal program will run from June 18th to August 11th.
June 18th -19th the scheduled streets will be chipped (dates are approximate*)
Meridian Rd (Hyrum Area) COMPLETED
June 23rd - June 30th the scheduled streets/ areas will be chipped (dates are approximate*)
500 S, 540 S, 580 S, 620 S, 75 W, Canyon Rd, 300 E, 400 E, Foothill Dr (Providence City) 3100 N, 400 W, 300 W, 200 W, 2850 N (North Logan) COMPLETED
July 1st - 2nd the scheduled streets will be chipped (dates are approximate*)
3000 S, 2000 W, 3200 S (Nibley Area) COMPLETED 2600 S (Nibley), 2200 S, 1800 S, 3800 W (Young Ward Area) IN PROGRESS
July 7th - 9th the scheduled streets will be chipped (dates are approximate*)
Millville Canyon Rd (Millville), 7000 W (Newton), 12200 N (Cornish), 8600 W, 11000 N (Clarkston)
July 14th - 17th the scheduled streets/ areas will be chipped (dates are approximate*)
Clarkston Town, Center St (Trenton Town), Newton Town, Lewiston City, Richmond City
July 21st - 31st the scheduled streets will be chipped (dates are approximate*)
2400 E (Upper High Creek), 12100 N (Lower High Creek), 11800 N, 1400 E, 12400 N, 11600 N, 1200 E, 12800 N, 12700 N, 12600 N, 12400 N, 13400 N, 13000 N, (Cove Area), Main St. (Mendon)
Aug. 4th - 11th the scheduled streets/ areas will be chipped (dates are approximate*)
Providence City, River Heights, Wellsville City
*Please Note:
We do our best to follow the planned schedule as closely as possible. However, a variety of factors can affect this process, and last-minute changes may be necessary. Weather conditions, equipment issues, and projects or repairs from other departments can all impact the timeline.
We appreciate your patience and understanding as adjustments may occur. For the most current updates or if you have any questions or concerns, please call us at 435-755-1650.
2025 Map
Click on the map below to view the County streets being resurfaced.